>I have been asked by a friend to build 2 entire walls of bookcases. Since I can only work on the weekends during daylight, it's going to take some time. I don't have room to hold all the cut parts until time to assemble them all at once.
My thought was to build 2 or 3 units at a time and install them, then build and install another batch as time allows. With this in mind, how would you level them? A loose toe kick for each batch, adjustable legs, or? Also cheap is good, as long as it's good.
>I am faced by a similar, if smaller, problem. As soon as I get done priming the new drywall in my rehabilitated recreation room / library I need to put in a run of 187" of continuous bookcases. My plan, after much consideration, is to divide it into 6 bays to be built essentially separately in my limited shop space. I intend to lay down a framework of on-edge 2X4s as the base and shim all if that level before starting anything else. I'm going for a relatively modern look and will be making the stiles 2.25" with matching rails and shelf fronts. I'll paint the front 2X4 black and allow the bottom rails on the cabinets to overhang them by a couple of inches to create a shadow-line at the floor level that may eventually receive a hidden rope light. My thought is that if the supporting structure is straight and level and if I am consistent in the cutting for the carcases there should be little problem fitting them in one-by-one.
>Those appear to be the sort that I use for kitchen cabinets. I don't know that I'd trust them, at least the plastic sort, for a book case where a really heavy load is a possibility. If adjustability is needed then there are heavier duty metal leveling feet of various sorts and I'd consider those before plastic.
>My son took on an Eagle project that was 17 bookcases for a library in his synagogue. The building dates to the early 1900's so you can imagine what the floor was like. We were faced with the same problems of limited space as well. We ended up installing them as we went. I cut some hardwood shims which we used to make sure that the bookcases stood against the wall. As far as the slope of the floor from side to side, that was not much of a issue so we never had to address it. We were blessed with the flooring the chose, carpet, which hid the shims. Good luck!
>I have built several libraries in my day and I would suggest that you build a plinth, as John suggests, install it, and then simply set your cabinets (bookcases) at whatever pace works for you and the client. If it were me, I would build all the stuff over however long a period, then take everything to the job site and install it in a day, rather than have your customer live with a work in progress.
One trick you might want to consider if you haven't already: Let the face frame of one cabinet overlap the stile of the previous cabinet so you get a seamless installation without having to apply those moldings after you install the cabinet.
Another thing: When you are measuring the room, allow a certain amount of scribe space to the ceiling as well as any confining walls and build your cabinets accordingly. Apply and finish the scribe strips with the rest of the cabinets, and scribe and cut them on the job to get a perfect fit to the walls and ceilings.
>I appreciate all of your comments (well almost all of them). If I had the room I would cut all the parts and them assemble them at once, however I don't have enough room for just the parts.
I'm still trying to decide if I will install the full toe kick and then set the cases on them as I finish them, or install one for each batch of cases when I install them.
If I install the full one then I will be under pressure to get the whole run completed and I don't really want to put up with that. As I said, this is for a friend (freebie), perhaps I'll ask them.