New Shop Started
Stuart Johnson
>I have finally started to see some progress on having a shop built. It has been like pulling teeth to even get responses from contractors let alone bids. This shows the start of the slab. What it shows is twelve loads out of a total of nineteen. There is about a four foot drop from the front to the back. The bottom photo shows what it looked like to start. In time this will be a 30x40 metal prefab. Then the works starts as my current shop (large 2 car garage) will be remodeled into a sewing "studio" for Fran.