>The logistics of this in such a short time are staggering. On day 1, you could drill 300 holes in 300 blanks and unwrap all 300 stoppers. I suppose that if you didn't turn them start to finish (sanding and finished...), you could easily bang out 30-50 a day for a week. At the end of the week, you'd have a bag of knobs and finials.
Then, you could remount them and sand them over the course of the next week, taking care to place them carefully somewhere before final spraying. Lastly, a few big batches on a board with screws driven through it to be able to spray and rotate...
It's doable, but not by me. Like John, I shoot myself after the first dozen. And it would cost $10K to do it with materials...