How long to build a drawer?
Derek Cohen (in Perth, Australia)
As I am building a total of 12 drawers, I have been conscious of the total amount of time it will take to complete the lot.
It is difficult to be accurate about the time expended on each drawer since the parts were prepared in three sessions (first resawing and thicknessing the boards, and then their dimensioning, and finally building the slips).
The first drawer, nevertheless, must have taken about 6 hours from dovetailing and to fitting. In spite of the accurate sawing and all dovetails going together off the saw, plus the use of the chisel knife trick, chopping the Jarrah waste was very time consuming.
Even though I was aware that my speed would increase, at 6 hours x 12 drawers it could still take several weeks.
The second drawer took 4 1/2 hours.
I read an article by Richard Jones in which he wrote:
A drawer like this takes a skilled craftsman between seven and eight hours to make and to shoot in precisely to the drawer opening. If multiples of similar drawers of this basic pattern are made the time element can be brought down to about 6-1/2 hours per drawer. Staining and polishing procedures take about another hour. If hardware involves fitting a lock and escutcheon in additiion to fitting a simple proprietary pull, about another two hours has to be allowed. Fancy veneered fronts with inlays and stringing and other traditional features such as cockbeads add yet more time. The skills required to build all these traditional drawer patterns need to be well developed, and it can be seen that a very elaborate drawer may take nearly sixteen hours to make.
Link: http://curve.phpwebhosting.com/~luka/articles/drawers/rjones1.html
I felt a little better after this, but there is still some way to go.
What time frames do you experience?
Regards from Perth
Derek
I imagine given the speed FK got up to speed in this country, that he didn't have that problem.