Re: Simple question
Grant in Iowa
Barry is right on the money here. You are describing Architectural style shingles. I have done about 15 roofs with this type of shingle and now much prefer them over 3 tabs. I worked under a pro roofer as an assistant during busy times here in Iowa. Now is a good time to say that roofing techniques vary slightly regionally, due to prevailing weather conditions and construction techniques.
Here's how we start:
Drip edge goes on the bottom edge of the roof first. Ice barrier for the bottom course and in any valleys overlapping this drip edge. On some known problem roofs, we do ice shield over the whole thing. Tar paper above the first course of Ice barrier. Take the time to get the lines straight on your tar paper as they will serve as a "sanity check" guide as you go up the roof to keeping them straight. Drip edge goes over the tar paper on the pitched edges. Next, a starter coarse, which is a continuous roll of self adhesive material designed to protect the roof from the gaps in the following coarse. You might think you are saving a buck by omitting this material, but it is cheaper than a second course of shingles you would otherwise use.
Now, Install a full shingle in the lower left corner of the roof, its lower edge flush or slightly overhanging the starter strip. Next comes a 2/3 shingle above that, a half shingle above that, then a 1/3 shingle above that. Go back to the bottom and to the right of the first full shingle and install a full shingle to its right, then a full shingle to the right of each partial shingle listed above. Now place a full shingle above the 1/3 shingle, then another 2/3, a 1/2, and another 1/3. Doing it this way prevents excessing walking on the shingles, which is hard on them. It is also MUCH faster than running 1 course all the way across like a typewriter. We will often set up a scaffold and do the bottom 5 or so courses from the scaffold. This is easier and safer than trying to stand upside down next to the edge of the roof.
Periodically check your straightness by either sighting from and end or by comparing the top row of shingles to the tar paper lines. Any errors should be gradually worked out over several courses so as to show minimally.
As I read your question, this should answer it. Don't forget to step flash as you go if you have a vertical wall on the left. I like the Henry's bead near the right edge of each piece of flashing, though I have seen many roofs without any that worked fine. Can't hurt, that is for sure.
Run your air nailer hose up over the peak of the roof, then back to yourself so you don't have to hold the weight of the hose as you go.
To your question of the far end of the roof and how to end shingles, what we usually do is shingle to where a single piece will cover the remainder, measure the gap and cut a shingle (usually a guy designated as shingle cutter does this on the ground and "Frisbees" it up to us.), and install that shingle. If the end shingle would be less than about ten inches in length, we actually install the short piece a shingle away from the end so it won't blow off in a storm. An if it is shorter than about 6 inches, we will usually avoid using a narrow shingle by using a couple offcuts from previous courses instead of a full to make up the difference. You can usually do it in two pieces. This all disappears in the finished roof, and so long as you avoid lining up the ends of two successive courses above each other, you will be fine in terms of weather proofing. The shingle cutter is also in charge of always cutting what he needs from the shortest possible remaining piece of scrap to save materials. Done right, a roof can be completed with an arm load of small pieces remaining.
Wear sneakers on the roof to avoid damaging the shingles with hard edged boots. Easier to bend over too.
FWIW,
Grant in Iowa