Shop progress
Bob
I am in the last stage of putting up the ceiling in the shop and should be done buy the end of Feb. I have to pick up a sheet rock lift in two weeks and buy 21 sheets of 5/8" fire code sheet rock. I finished the cribbing and put up 800 sq. feet of insulation this week. here are a few photos of how it came out so far.
From above