>I have a question that in my mind seems obvious but my brain is locked up. I have a set of plans for another clock and included is a cut list of primary wood and secondary wood parts. Unlike other plans I have followed, there is no total number listed for the approx bd. ft. required. For example a 4/4�5�x36� = 1.25 bd ft. Do I just keep adding them all up and metally try to �lay those parts out� on a board? I know it sounds simple, maybe that�s what I am struggling with, it is too simple :) Thanks, Rick
>The cutlist has the final size on it for each part. If this is correct then I would add up all the parts then add another 10 to 15% for cuts and working around knots etc. I would then take the total BF and head to the lumber mill and select the best stock for the job. Keep in mind while looking at the lumber what parts will show and and select accordingly. So if there is a large front panel then I would make sure I had a nice grain to a few piece of wood to show off on the panel. If they are all narrow parts not much wood showing then I would not worry so much about highly figured lumber and go more for a straight grain. What I really hate is when I see a knot cut in half and joined to another piece in the middle of a panel. So that is my way of doing it Have Fun
I have friends that apparently think there is lumber sitting in my shop that just happened to be the right size and thickness and then I just whack the ends off and put it together. And it all matches.
I have a stash of walnut and what I do is make a really gross estimate (like board feet in each surface) and then go get about twice that much from the stash.
Probably what you need to do is think through a cut list. Either draw out you parts or imagine how you would cut them from what size pieces of lumber. IE, you might be able to get all the stile and rail parts for the doors out of a 4/4 X 8" by 72" or two 4/4 X 4" by 72" , but you need a piece ten inches wide to make the panels. Obviously, this can be much more complex with a complicated project. It might be risky to buy too little lumber. You might have to make additional trips to the store and worse, they may have sold out or may not have wood that matches well.
So I think the answer is that this is harder than it first appears.
>Rick, a lot depends on the grade of lumber you have / purchase. In reality the cost of the lumber is pretty low in a project if you figure your time is at all valuable. That said I use "tree run" lumber for most projects (most of the lumber I have I have purchased from auctions / air dried, often complete trees that have been sawn up). This means I have some select and better, some #1 & 2 common etc. The lower grades of lumber are often so much cheaper that you can buy quite a bit more and select what you need. The grade of lumber does NOT relate to the quality of the finished product - but rather the amount/size of defect free cutting you can get from a board. I'm certainly not an expert, but what I am saying is that a lower grade 12" wide 6' long board made have one piece that is defect free 8" wide X 3' long or 6" wide X 6' long (knots / blemishes may prevent you from cutting any larger piece. The remainder may yield smaller parts - cutting around the blemishes. However, if you are needing smaller size finished boards, you may get almost as many from the worst grade vs select grade (and pay a lot less). When I do buy a special wood and need large boards, I make a note of what I need and carefully inspect the lumber before purchasing. I usually figure at least 30% of the material I purchase will be offcuts, often 40%. Of course I do make some spare parts as I work on a project. If I need 6 stiles for doors, I will make at least one spare. That way I don't have to reset up the router table etc., if I find one I don't like later (or if I screw one up - happens too often :~). In your case I would list the sizes of the larger parts, purchase the boards for these selecting defect free areas of material large enough to make these - then ballpark the rest at listed bf + at least 30%. A second trip to the lumberyard is more expensive then the extra wood cost and you know you have matching stock.
While it is likely overkill for one project, the trial download of CutList Plus might be useful. I found that it is very useful for sheet goods, but less so for lumber because of defects etc. However, it will get you in the ballpark. IIRC there were some limits on the trial version regarding the number of pieces you can enter, but maybe you can "fool" the software into thinking you have a number of separate projects. As you likely know, some magazine project plans give you the board feet and the layout which I find very useful and sure saves some time. Otherwise, what others have advised is pretty much how I would approach your project, especially wrt the most important/visible board(s) in your clock. Good luck.
>Rick, I don't know what this clock looks like, but it sounds like it might be a project where you can practically eyeball the amount of wood needed. Estimate the square footage of visible wood on the front, top and two sides, add a factor for waste and buy that many square feet. I've found that waste factors can vary considerably depending on the species and grade. Mahogany, for example, usually has very little waste, say 10% for cutoffs, while species or grades with a lot of knots and/or sapwood or wane edge might have 30% or more.
On projects where each piece must be carefully chosen for grain or figure or dimension, you will have to get more involved in your choice of wood. List the pieces that simply must be a certain size or figure, or made of boards of a certain width (such as door panels), and find individual boards that will give you these pieces, regardless of whether you can use the leftovers. Then rough estimate the balance of the order, add your waste factor (I'd say 20% on average).
>Thanks to all for the information, something to think about, all suggestions are good ones. I had thought briefly about the CutList software but have always used it for panels not "sticks". This is the part where patience comes in instead of going out to the shop and just start hacking up boards :) Thanks Again
>Thanks Ellis for your input as well. I checked out the Cut List program and put in a couple of dimensions and the output shows the location of the pieces on a board of a given length and width, an estimate I am sure, but it got me headed in the right direction. Will be certain the extra 10 to 20% depending on what wood I choose to build the clock. Rick