>I've made some brick paver paths in the past and run the whole process: tear out the concrete, several inches of gravel, compact it, 1" sand, install pavers.
This time, I am thinking about jsut putting the brick pavers right on top of the concrete path - it will actually work better in terms of its final height. In my mind, this saves hours of back breaking labor of tear-out of concrete and hauling gravel. My question is, should I glue the stones down to the concrete, or still place them in a thin bedding of sand on top of the concrete? Any input is appreciates
>The one (and only time) I've "assisted" on something like this, we etched the surface of the concrete and then troweled on a relatively thick coating of "mud" and placed the bricks on top of it. We used a fairly wet mortar as I recall. Maybe an adhesive would work also.
>IRRC, there are two ways of doing this. The gravel bed with the loose laid brick on top called the Flexible method(?) I think. The concrete base with the brick mortared to it, called the Rigid method, again, I think.
If the gravel base provides good drainage, the Flexible method works well because the gravel fails to hold enough water to suffer from a frost heave. This is sort of the "reed before the wind" theory.
The other method is based on brute strength.
I would suggest you put a later of sand on the concrete and lay your brick on that. If I did, I would not mortar the joints, I would also provide some sort of binder strip around the edges to prevent the brick migrating away in all directions. You can buy edge binding made of some sort of fiberglass or plastic that is a sort of L shaped piece. The long leg of the L goes under the brick and the short legs sticks up to confine the brick. Another choice would be to dig a narrow trench on both sides of the walk and stand a row of bricks up on their ends in the trench. The tops of them would be even with the top of the walk. A soldier course. When I did this, I made a screed that had a notch in each end and was curved on the bottom. After putting the soldier course or binding in place use the screed to level the sand. Only, the sand is not level, it is raised in the center, so that the water will drain off both sides of the walk.
Where we had a patio, we mortared the edge course in place, to the existing concrete, and sand-laid the center area. We laid the walkways over the compacted rock/sand base, with plastic edging.
What the landscape fellows did on the front yard work was mostly over compacted rock base, but also over the walkway. That's holding up pretty well after 6 or 8 years now, too. We used a tumbled concrete paver stone, nominal 2" thickness, IIRC. After our project got done, 5 or 6 of the neighbors liked it well enough that they did similar projects as well.